Water line update

An update on the water line project for the Jarvis/Lago area in Lake Sarasota from the county utilities coordinator:
On August 24 [the Lake Sarasota water line project] will be advertised for bids. One month is allowed for responses so there will be a bid opening near the end of September.

The bids will be reviewed and the qualified bidder selected. Then the contact goes to the Sarasota Board of County Commissioners in order to be signed.

It is anticipated that by the end of November the contract will be awarded and then the contractor has 120 days to complete the project so it should be done by the end of March.

We have been working on this project and trying to coordinate it with sidewalks. We realize that you have been waiting a long time and we appreciate your continued patience.

Please feel free to contact me if you have further questions.

Linda Seashore Larsen
Administrative Assistant IV
Community Outreach Coordinator
Program Management
llarsen@scgov.net
941-861-0662

Comments

Popular posts from this blog

Workshop: Development on West Side of Lake Sarasota 7.18.23

West Bridge meeting summary and next steps

Sarasota Baptist's planned development: Careless? Indifferent? Dangerous?